On behalf of Netze BW, we installed new power lines and a micro-tube system.
Two power lines were laid in a 130-meter-long trench. These were a low-voltage cable of the type NAYY 4×150 and a medium-voltage cable of the type NA2XS2Y 3x1x300. After installation, the cables were stored in a substation to be connected by a specialized contractor. We also installed a PE HD 4×20/15 micro-tube assembly in the same trench for future broadband expansions.
In addition, we were able to install a telecommunications conduit alongside an existing one.
Most of the route included a bike path, which was repaved to its full width (2.10 m) at the request of the municipality.