Date

2019

Category

Stadt-Winnenden_Marktplatz_Pressestelle-Winnenden

On behalf of Netze BW, we connected two buildings to the existing gas network.

Work was initiated to lay a new gas line in a 50-meter-long trench in order to provide gas service to two additional houses. The loamy subsoil proved to be a particular challenge. In addition, manual excavation had to be performed directly next to the houses to avoid damaging the masonry.

A specialized company was hired to create openings in the walls leading into the houses.

The trench was maintained at the standard width (0.6 m at the surface) along its entire length.